This project is the product of an unbundling initiative undertaken by the Illinois Tollway to encourage participation by small businesses

All Proposals must be on forms prescribed by the Illinois Tollway and must comply with the terms and conditions set forth in the Contract Documents. Copies of the plans, special provisions, proposal forms and other Contract Documents for this Contract are available from Accurate Repro, Inc. and can be viewed and/or ordered for purchase by visiting the On-line Plan Room via www.illinoistollwayplanroom.com.  Note that registration is required.

Plans are also available through the following organizations:  African American Contractors Association, Black Contractors United, Chicago Minority Business Development Council, Chicago Urban League, Federation of Women Contractors, Hispanic American Construction Industry Association, Illinois Hispanic Chamber of Commerce, Latin American Chamber of Commerce, Rainbow Push Coalition, Rock Valley College/Procurement Technical Assistance Center and Suburban Minority Contractors Association.

Sealed Proposals due November 14, 2013 at 10:30 a.m. local time

Proposals will be opened and the bids read aloud

Illinois Tollway Central Administration Building

2700 Ogden Avenue, Downers Grove, Illinois 60515

 

An Optional Pre-Bid Meeting October 24,  2013 at 10:00 a.m. local time

Illinois Tollway Central Administration Building

Engineering Conference Room 219

2700 Ogden Avenue, Downers Grove, Illinois 60515

 

Work start date                  On or about February 14, 2014

Completion date                 August 29, 2014

 

Questions                               October 28, 2013no later than 4:00 p.m. local time

Attention: A.J. Pebler

Email:  apebler@getipass.com

 

The work under this Contract shall consist of: pavement removal, curb and gutter removal and replacement, subbase granular material, PCC pavement, PCC medians, storm sewer construction, trench backfill, PC sidewalk and driveways, traffic signals, traffic signal interconnection, roadway lighting, signing, pavement marking, restoration (topsoil and sod) maintenance of traffic during construction. The work under this Contract shall be performed along the Tri-State Tollway (I-294) between Mile Post 8.15 and Mile Post 8.30 Cook County, Illinois Bidders are also required be registered, or submit evidence of application, with the Illinois Department of Human Rights (IDHR). There are NO EXCEPTIONS.